On 19 November, Construction Management reported that Herne Group, a Wigan-based consultancy working on nuclear, defence, energy and infrastructure programmes, has generated £14m in 'acceleration value' using AI-enabled scheduling software from Nodes & Links. The centrepiece is a single defence project. A client-instructed scope change pushed the forecast completion past a fixed deadline, and a risk analysis put the chance of hitting the planned date at 0.2%.

Most AI stories reaching project teams this year have been about documents. A fortnight earlier, the same title reported that Mott MacDonald staff had built more than 8,000 AI agents in Microsoft Copilot. Herne's story is different because the software is working on the programme itself, the document that planners, project managers, commercial teams and clients argue over every month.

It's worth examining more closely, rather than taking it at face value. Every figure in the article comes from Herne or Nodes & Links, and the two firms have been formal partners since May.

What Herne says happened

1. The problem

The client's change added scope to what CM describes as an asset of national importance, but the deadline remained unchanged. A 1,000-iteration probabilistic risk analysis run in the Nodes & Links platform put the probability of meeting the planned completion date at just 0.2%. Slippage was costing around £80,000 a day, according to the article.

2. Finding a way to recover time

With completion already slipping, Herne asked the platform a direct question: what options were available to recover the live schedule?

The software identified and modelled several possible interventions:

  • Extended working hours

  • Fast-tracking

  • Changes to schedule logic

  • Earlier completion of documentation

  • Resequencing of activities

The initial analysis identified scenarios offering up to 39 calendar days of potential recovery.

3. From analysis to action

Herne's team then assessed the options against resource availability, cost, sequencing constraints and client requirements.

The most impactful measure at that stage was moving selected critical commissioning activities from a five-day to a seven-day working week. The client agreed to the change.

4. What changed

The results emerged over the following months:

  • 15 days: Improvement delivered by the next schedule update.

  • 10 weeks: The P50 completion forecast moved forward within three months.

  • 8 weeks: Recovery supported by the overall intervention.

  • £4m+: Claimed acceleration-related savings, according to CM.

Three stat panels: 0.2% chance of meeting the planned completion date, 8 weeks of schedule recovery, P50 completion forecast moved forward 10 weeks within three months. Figures supplied by Herne Group and Nodes & Links.

The defence-project figures as reported by Construction Management on 19 November 2026. They are Herne's and Nodes & Links' own and have not been independently audited.

How to read 0.2% and P50

A conventional programme gives each activity one duration and produces one completion date. A probabilistic schedule risk analysis, usually called a QSRA, gives each activity a range (minimum, most likely, maximum), adds the events in the risk register with a probability and an impact, and then runs the programme many times with different values drawn on each run.

The Monte Carlo simulation produced a range of possible completion dates, showing how likely the project was to meet its original deadline.

A 0.2% result from 1,000 iterations means two of the thousand simulated runs finished by the planned date. The P50 is the date by which half the runs have finished, so it is an even-money forecast.

A P50 that moves forward by 10 weeks is a real shift in the middle of the distribution. It does not tell us the probability of meeting the required date today, and the article does not give that figure. Nor does it explain how the 15 days, the eight weeks and the 10 weeks relate to one another.

What the AI adds to a conventional QSRA

The simulation itself is established practice. Nodes & Links calls its engine 'industry-standard Monte Carlo', and researchers from the University of Leeds, writing in the RICS Construction Journal in September, described QSRA as 'almost routine'.

On the vendor's own account, the AI does two things around that engine. It proposes the three-point duration estimates for each activity 'from how similar completed work actually performed', which a planner can review and override. Its 'AI Mode' also lets a team put plain-language questions to a live schedule, runs them through the underlying models and records the reasoning behind each answer.

The Herne case study is mainly about the second: searching for recovery options and showing the working. Neither source says whether AI-assigned durations sat behind the 0.2% figure.

People still did the judging: Herne's practitioners decided which options were practical, and the client approved the seven-day week. Herne's project controls director describes the appeal.

❝

There is no other software out there that allows us to interrogate a live programme in this way and quickly identify where intervention is possible, where delivery performance can be improved, and where recovery and acceleration opportunities genuinely exist.

Andy Garnett, Project Controls Director, The Herne Group

For a planner, the claim to test here is the speed of interrogation: how quickly the tool answers a 'what if' that would otherwise take days of manual scenario building. It is also a partner's endorsement. The same sentence appears in the announcement Herne published on 13 May, when it formed what it called a 'strategic technology partnership' with Nodes & Links.

Whose numbers are these

The CM piece carries a 'CM Digital Staff' byline and is not labelled as sponsored, but it follows the customer story on Nodes & Links' website closely and uses the vendor's image. Three things follow for anyone tempted to quote it in a business case.

  • None of the figures has been independently audited, the client is unnamed, and neither source defines 'acceleration value' or shows how the £4m and £14m were calculated.

  • The £14m is not the defence project: CM presents it as a total from Herne's use of the platform across its projects, and the vendor's case study says 'across multiple projects'.

  • Herne's own website tells it differently, crediting 'more than £14 million of cumulative delay-related costs' avoided to one live programme over six months, and the public material does not say whether this is the same £14m.

❝

Herne is 'a perfect example of where project controls is heading'.

Greg Lawton, Nodes & Links' chief executive and co-founder

Greg may be proved right. For now this is one confidential case study told by a supplier and its partner, which makes it a lead to follow up and too thin to carry an investment decision.

What your own schedule would need first

A Monte Carlo run is only as good as the programme and risk data underneath it. Nodes & Links says as much on its product page: 'Results are only as good as the logic underneath.' The Leeds researchers tested their ideas on a focus group of ten senior practitioners, who raised the subjectivity of risk likelihood and impact estimates and the danger that inputs could be used to support a predetermined output.

The authors, led by Dr Grzegorz Grzeszczyk, put the wider problem bluntly: 'Project data is notoriously contentious, fragmented, and incomplete.'

Public clients are asking for the same kind of foresight. Becky Wood, chief executive of NISTA, said in July that its delivery confidence ratings for major government projects provide an early warning, helping identify risks sooner. NISTA has also introduced an AI-powered Early Warning System that draws on data from its project portfolio. At the end of March 2026, 29 projects in that portfolio (15%) were rated Green. A client that thinks in confidence levels will expect its consultants and contractors to do the same.

Takeaway

Herne's client instructed a change, and Herne was able to put a number on the damage and a tested set of options in front of that client while there was still time to act. If a scope change landed on your programme next month, the test is whether your risk analysis would show the date had become a long shot before the client told you.

Before any tool of this kind can help, there are four questions to put to your own data and to any vendor.

  • Is the programme logic sound, or are there open ends, hard constraints and long lags that would distort a simulation?

  • Is progress updated often enough, and honestly enough, does this month's forecast reflect what is happening on site?

  • Is the risk register mapped to programme activities, with probabilities and impacts that someone on the team would defend?

  • When a vendor quotes a recovery figure, can it show the probability of hitting the date before and after, and the working behind both?